Thursday, March 25, 2010

Vista Cay - Final Day

The whole project has now been completed. Everything has been cleaned up and all the furniture restored to its original positions.

THE DEN


MASTER BATHROOM


BEDROOM


ALTERED BEDROOM


LOUNGE


DINNING ROOM


2ND BATHROOM

THANK YOU FOR THE PRIVALAGE AND OPPORTUNITY IN ALLOWING

TO REMODEL YOUR HOME




Tuesday, March 23, 2010

Vista Cay - Days Eight & Nine

Bi-fold doors have been installed in the new closet

The painters have started - the dining room

... Old bedroom doorway

... Master Bedroom

... Master Bedroom closet

... Master Bathroom

Master Bedroom Closet Finished

Master Bedroom Finished

Thursday, March 18, 2010

Vista Cay - Days Six & Seven

The water heater has been moved to its new home

The crown molding has been finished in the laundry room

The ceiling and walls have been screened off ready for spraying texture

The new closet has been textured

... so has the new dining room wall

The painters came in and primered the texture

The bedroom door has been fitted

... so has the passageway door

... and the new toilet door

Thursday, March 11, 2010

Vista Cay - Days Four and Five

Bedroom to Bathroom door ready to be removed

Door taken out and jams cleaned

Door replaced and ready for final trimming

Toilet entrance framed and ready for drywall

Drywall attached

taped, floated and ready for skimming

Dining room wall framed and ready for drywall

Dining room wall - drywall up on one side

... and the other side

Dining Room doorway framed and drywalled

New Closet taped and floated

Closet with first drywall skim

New Bedroom doorway taped and floated

... with first skim

new Passageway doorway taped, floated and first skimmed

old bedroom doorway skimmed

new TV Cable in it's channel in the closet

TV Cable running through the laundry room

... look! cable no more

TV Cable in the Dining Room

TV Cable - tested and working

TV Outlet in the Dining Room