Wednesday, December 15, 2010

Willow Bend

View of Initial Damage to Drywall 

Damaged Flooring

Drywall Removed

Room Cleared

Water-Damaged Interior Framing

Water Entering the Home 

Water in the Home

Existing Framing has been Removed

Window Set Back In Place

Window Being Sealed on the Outside

Whilst Drilling a Hole to Secure the New Framing
We Found a Wall Cell Full of Water

New Wall Framing Installed

Wall Insulation Installed

Start of Drywall Install

Drywall Mud, Tape and Float

Starting the Floor Tiling 

Part-way There
  
Floor Tile Complete Except for Four Tiles

Applying Screed to Window Sills

Window Screened Off Ready for Texture

Last Four Tiles Laid

Grouting the Tile

Waiting for the Grout to Dry

Applying Wall Texture

Painting Window Recess and Sill 

Cutting-In the Walls

Painted Walls

Baseboard Installed

Sealing the Grout

The Finished Room